The Management of EUCL Ltd would like to inform the general public that new electricity connection services have been revised as follows:

 

Connection Processes and Stipulated Timeframes

Connection Process Category

Service delivery

Timeframes

Cost

Industrial area

and Industries located in 1km from the National grid

Submission of Application

1 Day

Free of charge

Field Survey

2 Days

Material Issuance, Construction & Installation

11 days

Free of charge

Testing & Commissioning

1 Day

Free of charge

 

Maximum 15 days

 

Industries between 1 and 5,3km to the National grid

Submission of Application

1 Day

 

Field Survey & Quotation

2 Days

Payments

1 Day

20,000,000 Rwf

Material Issuance Construction & Installation

10 Days

 

Installation, Testing & commissioning

1 Day

 

 

Maximum 15 days

 

Industries falling beyond 5,3km to the National grid

Submission  of Application

1 Day

 

Field Survey & Quotation

2 Days

Payments

1 Day

20,000,000 Rwf, for 1 to 5,3 km and 20,500,000 Rwf per km beyond 5,3 km

Material Issuance Construction & Installation

10 Days

 

Installation, Testing & commissioning

1 Day

 

 

Maximum 15 days

 

 